Providing the power for a moving experience

Providing the power for a moving experience

  • The Challenge

    A huge piece of equipment needs to be moved 22 kms to another site but power is anaccesible

  • The Solution

    Complete turnkey solution of power, standby power, and 24/7 refuelling and support for a 30 day move

  • The Impact

    Equipment was moved for the first time ever from mine to power station

Client:AGL Loy Yang

Location:Victoria, Australia

Sectors:Mining

The Challenge

Moving a stacker across a power station and mining site in an Australian first

AGL planned to relocate Loy Yang's travelling stacker, also known as the TS4, from its external overburden site into the base of the coal mine. But with no power of its own, getting it there would require some engineering and planning feats.

Project Fact File

22kmDistance to travel
2Loadbanks
30daysDuration of move
Aggreko offered a unique technology with a unique team at our disposal

AGL Loy Yang

Dump truck at