Engineered battery energy storage solution reduces generator runtime and fuel use

Client
Oil and gas infrastructure company
Location
Utah
Sector
Oil and gas

Overview

The challenge

Construction at a remote Utah gas plant depended on uninterrupted power 24 hours a day, seven days a week

The solution

Aggreko engineered a hybrid system combining four Tier 4 Final generators with approximately 1 MW of battery energy storage and temporary electrical distribution

The impact

The hybrid package maintained uninterrupted power around the clock while limiting generator operation to approximately three to four hours per day during the reported period

4Tier 4 Final generators
24/7Uninterrupted site power
3–4 HOURSApproximate generator runtime each day
1 MWBESS storage capacity