Hybrid energy solution cuts generator runtime, fuel use, and operating costs

Client
Water infrastructure provider
Location
Oklahoma
Sector
Oil and gas

Overview

The challenge

An Oklahoma water infrastructure provider needed reliable power to move produced water from oil and gas wells across the state

The solution

Aggreko engineered a hybrid power solution for two remote oilfield sites

The impact

At the converted sites, generator runtime fell from 24 hours a day to approximately three hours each day, a reduction of about 87.5%

24 → 3 hoursDaily generator operation after adding battery storage
87.5%Reduction in generator runtime
110 kW + 120 kWhTier 4 Final generator and BESS paired at each hybrid site