Keeping a naval vessel moving with reliable temporary power

Client
US defense and shipbuilding contractor
Location
Jacksonville, Florida, USA
Sector
Shipping

Overview

The challenge

A narrow operating window demanded reliable power and precise coordination

The solution

A compact, ship-ready power package built around the vessel’s unique requirements

The impact

Reliable temporary power kept the vessel moving and avoided costly alternatives

1500 kWTEMPORARY POWER CAPACITY TO SUPPORT VESSEL MOVEMENT
2 DAYSINSTALLATION AND COMMISSIONING ON A TIGHT TIDE-DEPENDENT SCHEDULE
1200 GALFUEL TANK CAPACITY SUPPORTING RELIABLE GENERATOR OPERATION

Loading component...