Ground view of wind turbine silhouettes against a pink sunset

Turbines tested with grid emulation

Turbines tested with grid emulation

  • The Challenge

    Wind farm needs power to quickly commission 122 turbines

  • The Solution

    3 MW temporary mini-grid lets turbine testing begin

  • The Impact

    Developer gets tick of approval and collects tax credit

Client:Wind farm developer

Location:USA

Sectors:Utilities

The Challenge

Commission 122 turbines with no grid power

A wind farm in the USA wanted 122 turbines constructed and fully operational within four months to qualify for a tax credit – a very tight timeframe. And it was made even trickier by the fact that grid power wasn’t scheduled for switch-on until later in the year. 
To get these turbines commissioned in time for the tax credit, the wind farm needed a reliable source of backfeed power, and fast, so they called us in to help.

122Turbines to test
3 MWTemporary mini-grid
400 kWPower per turbine
6,000 ftCabling

Loading component...

The Solution

Shared expertise and a 3 MW mini grid

The temporary substation we designed was a team effort. We worked with load bank experts ComRent, the developer, the turbine manufacturer and the electrical engineer of record to hatch a plan that would meet the site’s commissioning needs. That is, 400 kW and six hours of run time per turbine. All 122 of them.
We quickly installed a 3 MW temporary mini-grid complete with generators, load banks, circuit breakers, transformers, fuel tanks and more than 6,000 feet of electrical cable. And we had a specialist on-site throughout the entire commissioning process, for monitoring and maintenance. 

A great team effort. It goes to show how the right people working together can quickly get a complex power package installed in a remote environment.

[No text in field] ,

Loading component...

Loading component...

Loading component...

Loading component...

Loading component...