Turbines tested with grid emulation
Turbines tested with grid emulation
- The Challenge
Wind farm needs power to quickly commission 122 turbines
- The Solution
3 MW temporary mini-grid lets turbine testing begin
- The Impact
Developer gets tick of approval and collects tax credit
Client:Wind farm developer
Location:USA
Sectors:Utilities
The Challenge
Commission 122 turbines with no grid power
A wind farm in the USA wanted 122 turbines constructed and fully operational within four months to qualify for a tax credit – a very tight timeframe. And it was made even trickier by the fact that grid power wasn’t scheduled for switch-on until later in the year.
To get these turbines commissioned in time for the tax credit, the wind farm needed a reliable source of backfeed power, and fast, so they called us in to help.
Loading component...
The Solution
Shared expertise and a 3 MW mini grid
The temporary substation we designed was a team effort. We worked with load bank experts ComRent, the developer, the turbine manufacturer and the electrical engineer of record to hatch a plan that would meet the site’s commissioning needs. That is, 400 kW and six hours of run time per turbine. All 122 of them.
We quickly installed a 3 MW temporary mini-grid complete with generators, load banks, circuit breakers, transformers, fuel tanks and more than 6,000 feet of electrical cable. And we had a specialist on-site throughout the entire commissioning process, for monitoring and maintenance.