Power Supply to Meet Growing Demand in Peru.

Power Supply to Meet Growing Demand in Peru.

  • The Challenge

    Act quickly to generate power and support productive growth.

  • The Impact

    Power and productivity for the entire region.

  • The Solution

    Power and logistics solution delivered in record time

Client:A large-scale energy complex

Location:USVI - Saint Croix - Caribbean

The Challenge

Act quickly to generate power and support productive growth.

Peru's national power grid was facing a significant increase in energy demand within its concession area, leading to delays in transmission network and substation upgrades.

There was an urgent need to generate power at a critical distribution point to prevent shortages and sustain the region's productive growth.


KEY FACTS

19 MW – 22.9 kVof contracted capacity
19 generationunits installed
14-monthcontract

The Solution

Power and logistics solution delivered in record time.

Aggreko proposed and implemented athermal generation solution with a total capacity of 19 MW. The project included not only power supply but also full operational management, ensuring efficient and uninterrupted performance.

Equipment was strategically transported from Panama and Chile, showcasing Aggreko's logistical capabilities to rapidly mobilize resources.


Case Hidrandina_Corpo 965x716

The Impact

Power and productivity for the entire region.

The solution enabled 100% of the demand to be met during the region's peak productivity periods.

The benefits extended to multiple fruit companies and industries within the concession area, significantly improving their operations.