Power supply to meet growing demand in Peru
Power supply to meet growing demand in Peru
- The challenge
Act quickly to generate power and support productive growth.
- The solution
Power and logistics solution delivered in record time
- The impact
Power and productivity for the entire region.
Client:Power distribution company
Location:Trujillo, Peru
The Challenge
Act quickly to generate power and support productive growth
Peru's national power grid was facing a significant increase in energy demand within its concession area, leading to delays in transmission network and substation upgrades.
There was an urgent need to generate power at a critical distribution point to prevent shortages and sustain the region's productive growth.
The Solution
Power and logistics solution delivered in record time
Aggreko proposed and implemented athermal generation solution with a total capacity of 19 MW. The project included not only power supply but also full operational management, ensuring efficient and uninterrupted performance.
Equipment was strategically transported from Panama and Chile, showcasing Aggreko's logistical capabilities to rapidly mobilize resources.