Extra turnaround support at short notice
- The Challenge
Emergency AC and power provision after unit broke down during turnaround
- The Solution
Onsite within an hour to replace unit and provide further risk mitigation
- The Impact
Turnaround completed on time with no impact on production
Client:Petrochemical Plant
Location:Saudi Arabia
Sectors:Petrochemical and Refining
The Challenge
Emergency AC and power provision after unit broke down during turnaround
A Petrochemical Plant subcontractor had hired 4 Air Conditioning (AC) units from Aggreko to support them during a major turnaround at their customer’s petrochemical plant.
After one unit broke down, we were onsite within an hour with a replacement unit. At this point, with the turnaround already underway, the Petrochemical Plant realised they needed extra units of AC and power to mitigate any further risks across the plant during the Turnaround.
Any more failures would have affected production and potentially cost millions of dollars, including severe delays to the Turnaround.
Therefore the Petrochemical Plant requested directly that we provide additional AC units and power as soon as possible to ensure there was no downtime.