Helping TD Companies realize capital and expedite grid improvements

Helping T&D Companies realize capital and expedite grid improvements

Helping T&D Companies realize capital and expedite grid improvements

  • The Challenge

    The utility was looking for a way to complete their capital project while not impacting their customers

  • The Solution

    Providing temporary generation while our engineering team ensured the system was running flawlessly

  • The Impact

    Improved capital productivity and efficiency and reduced safety risks by removing live line work

Client:National Grid

Location:USA

Sectors:Utilities

The Challenge

Two Sub-Transmission lines needed pole replacement and re-conductoring without impacting the utility's customers

A radial sub-transmission system's poles were at the end of life and at risk of failure. New poles had been in place for over five years although they could not be re-conductored without an eight-hour outage. The utility was looking for a way to complete their capital project while not impacting their customers or their SAIDI & SAIFI metrics. When the field operations team heard what Aggreko was providing for the one system they identified, another location with a similar load and voltage asked for help. By bundling the jobs back to back, the utility was able to dramatically improve their productivity.


Key Facts

CapitalDeferred for 5 years
0Spills and human recordable events
0 SAIDI& SAIFI impact
“At Aggreko, we use our proven experience in temporary power generation to complete projects and save money."

Aggreko

Tags
  • Case Study
  • Utilities
  • North America
  • Power Generation