Powering a new plant during extensive delays

Powering a new plant during extensive delays

Powering a new plant during extensive delays

  • The challenge

    Providing power to a new midstream pipeline booster station project

  • The solution

    Design a temporary power solution quick

  • The impact

    Powering their business for 18 months straight

Client:Large midstream company

Location:Douglas, WY, USA

Sectors:Oil and gas

The Challenge

Providing power to a new midstream pipeline booster station project

A large midstream company was nearly ready to take their latest natural gas processing and treating plant live. They just needed power at their booster pump station. But their utility company kept stringing them along — even when the company offered to pay for poles, lines, and installation themselves. They estimated they would be forced to wait for at least two to three months. And without a clear answer on permanent power by utilities — and with all signs pointing to a longer delay than expected — the pressure built by the day. So, they reached out to Aggreko for help.

5x 1300 kWNatural gas-powered generators
5Gas liquid separators
24/7Remote monitoring
18 monthsContinuous temporary utilities

Loading component...

Loading component...

Loading component...

Loading component...

Loading component...

Loading component...