Emergency chiller for refinery
Emergency replacement chiller for refinery
- The Challenge
Get a refinery back online as quickly as possible
- The Solution
Replacement chiller and a 1,500 kW generator
- The Impact
Refinery back online in 12 hours, saving customer millions of dollars
Client:Chemical manufacturer
Location:USA
Sectors:Petrochemical and refining
The Challenge
Replace a plant’s failed chiller in a hurry
A Gulf coast chemical manufacturing plant had a catastrophic failure of one of its chillers, which shut down the entire plant. A shutdown like this can measure minutes in dollars and the plant manager estimated this one at $1,000,000 a day; there was a lot riding on finding a replacement chiller as quickly as possible.
To make matters worse, the failure happened on a weekend and hope was fading that a chiller with enough capacity could be found before Monday. Fortunately, we don’t let regular office hours get in the way of an emergency, and we took the call immediately.