Emergency chiller for refinery

Emergency replacement chiller for refinery

  • The Challenge

    Get a refinery back online as quickly as possible

  • The Solution

    Replacement chiller and a 1,500 kW generator

  • The Impact

    Refinery back online in 12 hours, saving customer millions of dollars

Client:Chemical manufacturer

Location:USA

Sectors:Petrochemical and refining

The Challenge

Replace a plant’s failed chiller in a hurry

A Gulf coast chemical manufacturing plant had a catastrophic failure of one of its chillers, which shut down the entire plant. A shutdown like this can measure minutes in dollars and the plant manager estimated this one at $1,000,000 a day; there was a lot riding on finding a replacement chiller as quickly as possible.

To make matters worse, the failure happened on a weekend and hope was fading that a chiller with enough capacity could be found before Monday. Fortunately, we don’t let regular office hours get in the way of an emergency, and we took the call immediately.

12 hoursTime to replace chiller
$1,000,000per day еstimated cost of shutdown
1 monthReplacement chiller uptime

Loading component...

Loading component...

“In this case, time was money – lots of it – and we knew we had to work quickly to get the replacement chiller operational.”